Signing a lease before a building is finished can secure premium space and favorable economics, but it transfers real risks — delivery timing, specification creep, landlord solvency, and legal exposure — that a fully occupied asset never carries. Understanding which questions to ask, and what answers to demand, is the difference between a successful pre-commitment and a costly one.

Why Pre-Commitment Leases Carry Unique Risk

A lease in a building under construction is fundamentally different from a lease in a standing asset. When you sign, the product you are committing to does not yet fully exist. The floor plan may change, the mechanical systems have not been tested, and the landlord's capital stack may not be complete.

The standard due diligence checklist a tenant-rep adviser uses for existing buildings does not translate directly. Zoning approvals, construction loan terms, contractor relationships, and delivery milestones all become material facts that belong in your underwriting, alongside the rent, term, and tenant improvement allowance.

Most experienced occupiers and their advisers treat a pre-commitment as a two-stage process: first, a rigorous vetting of the development itself; second, the lease negotiation that layers protective mechanisms directly into the agreement. These nine questions address both stages, in sequence, so you approach deal execution with a full picture rather than a partial one.

Question 1: What Is the Realistic Delivery Date — and What Does the Lease Say About It?

The projected delivery date in a marketing brochure is not a legal commitment. Developers routinely publish an estimated substantial completion date without ever writing that date into the lease with teeth attached. Your first obligation is to map the difference between what the developer is saying verbally and what the lease document actually states.

A well-negotiated lease should define substantial completion precisely — not just certificate of occupancy, but the specific punch-list threshold that triggers your rent commencement. It should also define what happens if the landlord misses that date. In many jurisdictions, the default is that rent simply does not start until delivery occurs, but that protection disappears when boilerplate language allows the landlord an unlimited cure period.

Negotiate a delivery deadline with real consequences. A common structure gives the landlord a grace period (frequently six to twelve months beyond the original date), after which the tenant earns the right to terminate the lease and recover its costs. This provision is sometimes called a termination right or a walk right. It is not standard; you must ask for it and document the reasoning in your negotiation record.

Also ask what the construction schedule actually looks like today, not at the time the marketing package was produced. Request the most recent owner's project schedule and compare the milestones to the lease dates. If the schedule already shows slippage, the stated delivery date is a fiction.

Question 2: Who Holds the Construction Loan, and Is It Fully Funded?

A development that runs out of money mid-construction does not simply pause — it enters a legal and financial spiral that can trap a tenant's signed lease in a lender's workout process for years. Before you sign, you need to understand the capital structure of the project.

Ask the developer to disclose the construction lender and the status of the loan. A fully committed and drawn construction facility is materially less risky than a development that is relying on a phased equity draw or a gap bridge facility. Developers may resist sharing lender identity, but sophisticated tenant-rep advisers routinely ask, and the willingness to answer is itself a signal about the developer's financial transparency.

Look for a non-disturbance agreement (NDA) or subordination, non-disturbance, and attornment agreement (SNDA) in the lease. An SNDA ensures that if the lender forecloses on the property, your lease survives. Without it, a lender who takes back the asset is under no obligation to honor your pre-commitment in many states, depending on how the mortgage priority is structured.

Also ask whether the equity partners behind the project are committed and funded. Developers frequently raise equity in tranches tied to construction milestones. If the next equity close has not happened, the project may be more speculative than the marketing suggests.

Question 3: What Exactly Is Included in the Base Building Specification?

The base building specification is a legal document that defines what the landlord is obligated to deliver at handover. It is not the same as the architect's design intent drawings, the marketing renderings, or the sales team's verbal assurances. Every detail that is not in the specification is a potential dispute.

Request the full base building specification — HVAC capacity, floor-to-ceiling height, raised floor or slab-to-slab structural load, power density at the floor plate, elevator count and speed, lobby finishes, and life-safety systems — in writing, before signing. Compare it line by line to what the leasing team has described. Any discrepancy is a negotiation point, not a minor administrative gap.

Pay particular attention to HVAC capacity and electrical power, especially if your operations are technology-intensive, life sciences-adjacent, or involve above-average occupancy density. Base building mechanical systems sized for a generic occupancy may be inadequate for your actual use. The cost to upgrade post-occupancy is typically your responsibility unless you negotiate for the upgrade to be included in the landlord's scope before the slab is poured.

Ask specifically what the landlord's fit-out allowance covers and what it does not. Tenant improvement allowances in pre-commitments are frequently structured as a dollar-per-rentable-square-foot cap. If the base building delivers a raw shell, the allowance may not reach a fully fitted state at today's construction costs, and the gap becomes a tenant capital obligation.

Question 4: What Are the Measurement Standards, and How Will the Final Rentable Area Be Calculated?

Rentable square footage in a building under construction is an estimate, not a fact. The final measured area is typically determined after construction using BOMA or another defined standard, and even small differences in that calculation have meaningful rent implications across a ten-year term.

Ask the lease to specify the measurement standard (BOMA 2017 is current in most U.S. markets), and ask for a right to commission your own independent measurement after handover. If the final measured area differs from the lease area by more than a defined threshold, the rent should adjust accordingly. This provision is not unusual, but it needs to be explicitly written into the agreement.

Also ask about load factor — the ratio of rentable to usable square footage — and how it was derived. In a building that has not been built, the common area estimate is a projection. If the building delivers with more common area than projected (larger lobbies, wider corridors, additional amenity floors), the load factor rises and your rent-per-usable-foot increases even if the base rent rate stays flat.

For large occupancies, a hypothetical example illustrates the exposure: on a 50,000 rentable square foot lease at $60 per foot, a one percent measurement variance translates to $30,000 per year in rent. Over a ten-year term, that is a $300,000 exposure before accounting for annual escalations. Negotiating a cap on measurement variance is a standard ask in a well-structured pre-commitment.

Question 5: What Permits and Approvals Are Outstanding?

Every building under construction has some entitlement or permitting step that has not yet been completed. The question is whether those outstanding approvals are ministerial (nearly certain to be granted) or discretionary (subject to public hearing, appeal, or political risk).

Request a permit and approvals log from the developer. It should list every required permit, the authority having jurisdiction, the current status, and the expected issuance date. If the core and shell building permit has been issued and the project is under construction, the residual permitting risk is typically low. If the building is in pre-development or early construction and a discretionary approval (variance, rezoning, special permit) is still open, the risk profile is materially different.

Ask specifically whether any third-party appeals are outstanding against the project's entitlements. In urban markets, neighbor or advocacy group appeals of environmental impact reviews or zoning variances are not unusual, and they can delay or in extreme cases invalidate a project. A developer who cannot answer this question directly is a developer whose legal team has not been transparent with the leasing team.

Also ask about the certificate of occupancy (CO) process. In some jurisdictions, occupying a building without a CO — even a temporary one — is a legal violation that can expose the tenant as well as the landlord. Your lease should make the landlord's delivery obligation conditional on obtaining all necessary occupancy approvals, not just substantial completion of construction.

Question 6: What Rights Do You Have If the Specifications Change?

Developers change building designs during construction. Sometimes the change is cosmetic; sometimes it is structural or mechanical. Without a written specification change protocol in your lease, you may have no rights when the landlord informs you at handover that the building you signed for is not exactly the building you are receiving.

Ask for a material change clause. This provision requires the landlord to notify you of any change to the base building specification above a defined materiality threshold, and gives you the right to approve, reject, or in some cases terminate if the change is substantial. What counts as material is a negotiated definition — a change to lobby finishes is different from a change to floor-to-floor height or structural load.

The more complex question is what recourse you have after a change is made without notice. If your space planning has already been executed on the assumption of a certain floor plate, and the developer reduces the core footprint after design development, your existing test-fit may no longer work. That is not an abstract risk; it has forced real occupiers into costly redesigns in the middle of their own tenant improvement programs.

Ask your architect to document the base building assumptions underlying your fit-out design and attach that documentation to the lease as an exhibit. It creates a clear baseline against which any subsequent change can be evaluated and priced.

Question 7: What Are the Landlord's Construction Warranties and Your Remedies for Defects?

A new building carries construction warranties from the general contractor and from subcontractors covering specific building systems. As a tenant, you are not a party to those contracts, and you have no direct rights under them unless the lease explicitly assigns or passes through those warranties to you.

Ask the landlord to provide a summary of the major construction warranties — roofing, mechanical, electrical, plumbing, curtain wall — including their durations and the contractors responsible. Then ask the lease to include a provision requiring the landlord to pursue warranty claims on your behalf, or to assign the relevant warranties directly to you if permitted under the construction contracts.

Also ask about the landlord's defect liability period. Many commercial leases contain a one-year defect notification period, after which the tenant's right to claim for latent construction defects is diminished or extinguished. Negotiate an extended period for latent defects — those that are not discoverable at handover — particularly for roofing, waterproofing, and structural elements that may not manifest for several years.

If the landlord is also providing the tenant improvement build-out, the warranty question extends to the fit-out work. Distinguish clearly between the base building warranty and the fit-out warranty, and ensure each has a named responsible party. Confusion between these two layers of warranty is a frequent source of disputes in year two or three of occupancy.

Question 8: What Happens to Your Lease If the Building Is Sold During Construction?

Developers frequently sell assets — sometimes at or before stabilization. If the building is sold during construction, or in the lease-up period before you take occupancy, your lease will be assigned to the new owner. That new owner may have different priorities, different capital resources, and different construction management practices.

Ask the lease to include a notification obligation requiring the landlord to inform you of any sale or assignment of the building during the construction period. This does not give you a termination right, but it gives you visibility so your legal counsel can review the SNDA position with the new owner's lender and confirm your lease protections transfer intact.

In some negotiations, tenants in anchor pre-commitments (typically above 20 to 30 percent of the building) successfully negotiate a consent right over assignment during construction, or at minimum an estoppel and confirmation process with any incoming owner. This is a harder ask for smaller tenants, but it reflects a legitimate risk that is worth raising.

The timing of a sale also affects who is responsible for delivering the tenant improvement allowance. If the developer sells before your tenant improvement work begins, ensure the purchase and sale agreement obligates the buyer to fund the allowance, and that the obligation is not buried in a schedule that the buyer's counsel can later contest. Having this confirmed in writing before you sign is cleaner than chasing it after the sale closes.

Question 9: How Will You Manage the Handover Process, and What Are Your Rights During Fit-Out?

The handover process — the transition from landlord-constructed base building to tenant-controlled fit-out — is operationally complex in a new building. Systems are still being commissioned, punch-list items are outstanding, and the building has not yet been occupied and stress-tested. How that period is managed directly affects your fit-out timeline and your move-in date.

Ask the lease to define a detailed handover protocol: notice requirements, the inspection period you are entitled to, the punch-list resolution process, and the conditions that must be satisfied before rent commences. Specifically ask what happens if punch-list items are not resolved by the time your tenant improvement contractor needs access. A common structure is to allow early access while holding back a portion of the rent commencement or retaining a landlord reserve against uncured items.

Ask whether you will have the right to perform your own commissioning review of base building systems — HVAC, life safety, electrical — before accepting handover. For large or technically complex occupancies, bringing a commissioning agent on behalf of the tenant is worth the cost many times over. Issues found before handover are the landlord's problem; issues found after are frequently yours.

Also clarify the access rights during your fit-out period. Will you have exclusive control of your floors, or will the landlord's contractor be simultaneously completing base building work in adjacent areas? Coordinating two construction programs in the same building creates scheduling conflicts, safety issues, and insurance complications. The lease should address who controls the construction schedule when both programs overlap, and who bears the cost of any delay caused by the other party's work.

Pulling the Nine Questions Into a Single Due-Diligence Framework

These questions are not independent checkboxes — they form a connected framework where the answer to one question shapes the others. The delivery date question connects directly to the construction loan status. The specification change clause connects to the measurement rights. The warranty terms connect to the handover protocol.

This is exactly where the difference between a transactional approach and a genuinely integrated deal-execution process becomes visible.

For occupiers evaluating multiple options in a competitive market, the ability to compare lease economics with assumptions in view matters as much as the negotiation itself.

What to Document Before and After Signing

Documentation discipline separates occupiers who have leverage in a construction-era dispute from those who do not. Before signing, your pre-commitment package should include the signed lease with all exhibits, the base building specification as a legal attachment, the approved construction schedule, the permit and approvals log, the SNDA from the construction lender, and any side letters regarding delivery milestones, tenant improvement funding, or specification warranties.

After signing, appoint someone internally — or instruct your tenant-rep adviser — to maintain a construction monitoring log that tracks milestone dates, change notifications from the landlord, any agreed modifications to the specification, and correspondence with the construction management team. This record is your evidence base if a dispute arises at handover or in the first year of occupancy.

Matching the Questions to Your Negotiation Strategy

Knowing these nine questions is only useful if you sequence them correctly in your negotiation. Not every question carries equal weight for every occupier. A technology company focused on power density will weight Question 3 and Question 7 differently than a professional services firm whose primary concern is delivery timing and presentation-quality finishes.

Before entering letter-of-intent negotiations, rank the nine questions by materiality to your specific use case. Work with your legal counsel and tenant-rep adviser to identify which answers are deal conditions (you will not sign without them) and which are negotiating positions (you prefer a certain outcome but will trade against other provisions). This hierarchy prevents the negotiation from becoming a war on every front simultaneously, which typically produces worse outcomes for the tenant.

The lease abstract should capture not just the final negotiated terms but the reasoning behind each protective provision. When your occupancy extends to year five and a dispute arises over a base building defect, the person handling the claim may not have been part of the original negotiation. A documented reasoning trail is an institutional asset, not an administrative burden.

Applying This Framework to Your Next Pre-Commitment

The discipline required to ask all nine of these questions — and to insist on substantive answers — is the same discipline that separates great commercial real estate advisers from average ones. Great advisers come to the table with a prepared list of questions tied to the specific development risk profile, not a generic checklist recycled from the last transaction.

The article's central argument is straightforward: answering the 9 Questions to Ask Before Signing a Lease in a Building Under Construction before you sign is not excessive caution — it is the minimum analytical standard for a decision that will govern your occupancy cost and operational continuity for a decade or more.

For teams building that standard into every pre-commitment,

About Advantai

Advantai is a commercial real estate intelligence and operations platform operated by ADVANTAGE AI LLC, a Delaware limited liability company. It connects client relationships, property research, documents and financial decisions in one workspace for commercial real estate teams — advisers and brokerage teams, occupier and facility teams, and portfolio teams. The platform covers CRM and origination, requirements and site selection, Property X-Ray (an interactive 3D building workspace), financial modeling and comparison, document intelligence, transactions and diligence, client collaboration, and portfolio strategy with critical dates. The optional Super Agent upgrade adds specialist, source-backed research and automated scenario analysis.

Get Started with Advantai

Ready to see your next move clearly? Go to advantaico.com, click Request a demo and tell us about your next project. Prefer to start with a single project? Visit advantaico.com/getting-started to plan your first one.

Take the next step in this workflow.

Request a product demo

Prepare your inputs with the first-project guide.

← Back to all insights